Zinc-rich primer, finish by others · برايمر زنك، والتشطيب بالموقع
Epoxy zinc-rich primer 60–80 µm
Installation
Fix supports first; add a support within 600 mm of each fitting.
Keep splice joints near supports, away from mid-span.
One splice plate each side, M6 round-head bolts, heads inside.
Bond the run to earth where the project specification requires.
Standards
Load data
Safe working loads and support spans will be published after type testing to IEC 61537. Until then, support spacing follows the project specification; our engineers can advise on typical spans for your cable load.
Preliminary datasheet for the TRUSTEEL launch range. Values may change before Rev A1; confirm with TRUSTEEL before ordering. Standards are listed as design and test references; compliance is claimed only where a test report is issued.